Rakentamisjärjestyksen valinta asuinkorttelituotannossa
Lahtela, Matias (2023)
Lahtela, Matias
2023
Johtamisen ja tietotekniikan DI-ohjelma - Master's Programme in Management and Information Technology
Johtamisen ja talouden tiedekunta - Faculty of Management and Business
This publication is copyrighted. You may download, display and print it for Your own personal use. Commercial use is prohibited.
Hyväksymispäivämäärä
2023-03-16
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi:tuni-202302282673
https://urn.fi/URN:NBN:fi:tuni-202302282673
Tiivistelmä
Asuinkorttelihanke on usean erillisen rakennusprojektin muodostama kokonaisuus, joka sisältää asuinkerrostaloja ja yhteisen ajoneuvojen pysäköintihallin. Asuinkorttelin rakentamisjärjestys valitaan rakennushankkeen suunnitteluvaiheen aikana, jossa hankkeen projekti- ja työpäällikkö vastaavat yhdessä rakentamisjärjestyksen suunnittelusta. Rakennushankkeen suunnitteluvaiheen päätökset vaikuttavat pitkälle asuinkorttelin toteutukseen, sillä asuinkorttelin rakentaminen kestää useita vuosia. Tuotannon näkökulmasta voidaan päätyä huonoon toteutusjärjestykseen, jos rakentamisjärjestyksen suunnitteluvaiheessa ei ole tunnistettu rakentamisjärjestyksen aiheuttamia vaikutuksia riittävän ajoissa tai tuotanto-organisaatio ei ole kommentoitu korttelihankkeen luonnossuunnitelmia ennen rakentamisjärjestyksen valintaa. Rakentamisjärjestyksen aiheuttamat ongelmat esiintyvät rakentamisvaiheessa erilaisina tuotannon häiriöinä, joiden vuoksi työmaaorganisaation täytyy toteuttaa erilaisia muutoksia suunnitelmissa, väliaikaisjärjestelyissä tai työn suunnittelussa.
Tutkimuksen tavoitteena on kehittää asuinkorttelituotannon rakentamisjärjestyksen suunnitteluvaihetta, että rakentamisjärjestyksen vaikutuksia voidaan arvioida aikaisemmin suunnitteluvaiheen aikana. Tutkimusongelmaan etsittiin vastauksia tutkimuskysymysten avulla, joilla selvitettiin rakentamisjärjestyksen suunnitteluvaihetta, rakentamisjärjestykseen vaikuttavia tekijöitä ja vaikutuksia sekä rakentamisjärjestyksen aiheuttamia haasteita rakentamisvaiheessa.
Tutkimus tehtiin kvalitatiivisena tapaustutkimuksena, joka koostui kirjallisuuskatsauksesta ja haastattelututkimuksesta. Kirjallisuuskatsaus sisältää projektinhallinnan ja rakennushankkeen hallinnan kirjallisuutta, jotka vaikuttavat rakentamisjärjestyksen valinnassa. Tutkimuksen haastattelut suoritettiin teemahaastatteluina, joihin valittiin kohdeyrityksestä ennalta valittuja työntekijöitä. Haastatteluita suoritettiin yhteensä yhdeksän kappaletta ja tutkimuksessa käsiteltiin yhteensä seitsemää eri asuinkorttelitapausta. Tutkimus rajattiin kohdeyrityksen pääkaupunkiseudun asuinkerrostalo tuotantoon, jossa yksi rakennusliike toteuttaa kaikki asuinkorttelin rakennukset.
Tutkimuksen tuloksien perusteella asuinkorttelien rakentamisjärjestyksien valintaan vaikutti viisi päätekijää: pelastautumisratkaisut, autohalli, logistiikka, sijainti sekä tilat ja alueet. Kaikki päätekijät täytyi huomioida aina rakentamisjärjestyksen suunnitteluvaiheessa ja jokainen tekijä vaikutti eri tavoilla toteutukseen. Rakentamisjärjestyksien toistuviksi tuotannon haasteiksi tunnistettiin puolestaan seuraavat viisi tekijää: logistiikka, resurssit, suunnitelmat, aikataulut ja turvallisuus. Tuloksien perusteella kohdeyritykselle ehdotettiin kehitysehdotuksia rakentamisjärjestyksen suunnitteluvaiheeseen ja projektin johtamisjärjestelmään.
Asuinkorttelihankkeen rakentamisjärjestykseen oli vaikea löytää yhtä oikeaa ratkaisua, koska kaikki rakennusprojektit ovat luonteeltaan ainutlaatuisia. Kuitenkin asuinkorttelin rakentamisjärjestyksen huolellinen suunnittelu ja erilaisten vaikutuksien tunnistaminen suunnitteluvaiheen aikana, mahdollistaa tuotannon näkökulmasta toteutettavan asuinkorttelin rakentamisjärjestyksen luomisen. The residential block project is a complex of several separate building projects, including apartment blocks and a shared car park. The construction sequence for a residential block is chosen during the design phase of the project, where the project manager and the site manager are together responsible for designing the construction sequence. Decisions are taken during the design phase of the project will have a major impact on the implementation of the residential block, which takes several years to build. From a production point of view, a poor implementation sequence can result if the effects of the construction sequence are not identified early enough in the planning phase or if the production organization has not commented on the draft plans for the block project before the construction sequence is chosen. The problems caused by the construction sequence occur during the construction phase in the form of various disruptions to production, which require the site organization to make various changes to the plans, temporary arrangements, or work scheduling.
The aim of the study is to develop the planning phase of the construction sequence for residential block production so that the effects of the construction sequence can be assessed earlier in the planning phase. The research problem was answered by means of research questions to identify the design phase of the construction sequence, the factors and effects of the construction sequence and the challenges posed by the construction sequence during the construction phase. The study was conducted as a qualitative case study consisting of a literature review and an interview study. The literature review includes literature on project management and construction project management that influence the choice of construction sequencing. The interviews for the study were conducted as thematic interviews with pre-selected employees from the target company. A total of nine interviews were conducted and the study covered a total of seven different residential block cases. The study was limited to the production of a residential block of flats in the metropolitan area of the target company, where one construction company carries out all the buildings in the block.
Based on the results of the study, five main factors influenced the choice of construction sequences for the residential blocks: rescue solutions, car park, logistics, location, facilities, and areas. All the main factors had to be taken into account at each stage of the design of the development sequence and each factor influenced the implementation in different ways. Five factors were identified as recurring production challenges for the construction sequences: logistics, resources, plans, schedules, and safety. Based on the results, suggestions were made to the target company to improve the planning phase of the construction sequence and the project management system.
It was difficult to find a one solution for the construction sequence of a residential block projects, because all construction projects are unique in nature. However, careful planning of the construction sequence of a residential block and identification of the different impacts during the planning phase will allow the creation of a feasible residential block construction sequence from a production point of view.
Tutkimuksen tavoitteena on kehittää asuinkorttelituotannon rakentamisjärjestyksen suunnitteluvaihetta, että rakentamisjärjestyksen vaikutuksia voidaan arvioida aikaisemmin suunnitteluvaiheen aikana. Tutkimusongelmaan etsittiin vastauksia tutkimuskysymysten avulla, joilla selvitettiin rakentamisjärjestyksen suunnitteluvaihetta, rakentamisjärjestykseen vaikuttavia tekijöitä ja vaikutuksia sekä rakentamisjärjestyksen aiheuttamia haasteita rakentamisvaiheessa.
Tutkimus tehtiin kvalitatiivisena tapaustutkimuksena, joka koostui kirjallisuuskatsauksesta ja haastattelututkimuksesta. Kirjallisuuskatsaus sisältää projektinhallinnan ja rakennushankkeen hallinnan kirjallisuutta, jotka vaikuttavat rakentamisjärjestyksen valinnassa. Tutkimuksen haastattelut suoritettiin teemahaastatteluina, joihin valittiin kohdeyrityksestä ennalta valittuja työntekijöitä. Haastatteluita suoritettiin yhteensä yhdeksän kappaletta ja tutkimuksessa käsiteltiin yhteensä seitsemää eri asuinkorttelitapausta. Tutkimus rajattiin kohdeyrityksen pääkaupunkiseudun asuinkerrostalo tuotantoon, jossa yksi rakennusliike toteuttaa kaikki asuinkorttelin rakennukset.
Tutkimuksen tuloksien perusteella asuinkorttelien rakentamisjärjestyksien valintaan vaikutti viisi päätekijää: pelastautumisratkaisut, autohalli, logistiikka, sijainti sekä tilat ja alueet. Kaikki päätekijät täytyi huomioida aina rakentamisjärjestyksen suunnitteluvaiheessa ja jokainen tekijä vaikutti eri tavoilla toteutukseen. Rakentamisjärjestyksien toistuviksi tuotannon haasteiksi tunnistettiin puolestaan seuraavat viisi tekijää: logistiikka, resurssit, suunnitelmat, aikataulut ja turvallisuus. Tuloksien perusteella kohdeyritykselle ehdotettiin kehitysehdotuksia rakentamisjärjestyksen suunnitteluvaiheeseen ja projektin johtamisjärjestelmään.
Asuinkorttelihankkeen rakentamisjärjestykseen oli vaikea löytää yhtä oikeaa ratkaisua, koska kaikki rakennusprojektit ovat luonteeltaan ainutlaatuisia. Kuitenkin asuinkorttelin rakentamisjärjestyksen huolellinen suunnittelu ja erilaisten vaikutuksien tunnistaminen suunnitteluvaiheen aikana, mahdollistaa tuotannon näkökulmasta toteutettavan asuinkorttelin rakentamisjärjestyksen luomisen.
The aim of the study is to develop the planning phase of the construction sequence for residential block production so that the effects of the construction sequence can be assessed earlier in the planning phase. The research problem was answered by means of research questions to identify the design phase of the construction sequence, the factors and effects of the construction sequence and the challenges posed by the construction sequence during the construction phase. The study was conducted as a qualitative case study consisting of a literature review and an interview study. The literature review includes literature on project management and construction project management that influence the choice of construction sequencing. The interviews for the study were conducted as thematic interviews with pre-selected employees from the target company. A total of nine interviews were conducted and the study covered a total of seven different residential block cases. The study was limited to the production of a residential block of flats in the metropolitan area of the target company, where one construction company carries out all the buildings in the block.
Based on the results of the study, five main factors influenced the choice of construction sequences for the residential blocks: rescue solutions, car park, logistics, location, facilities, and areas. All the main factors had to be taken into account at each stage of the design of the development sequence and each factor influenced the implementation in different ways. Five factors were identified as recurring production challenges for the construction sequences: logistics, resources, plans, schedules, and safety. Based on the results, suggestions were made to the target company to improve the planning phase of the construction sequence and the project management system.
It was difficult to find a one solution for the construction sequence of a residential block projects, because all construction projects are unique in nature. However, careful planning of the construction sequence of a residential block and identification of the different impacts during the planning phase will allow the creation of a feasible residential block construction sequence from a production point of view.