Measuring subcontractor work efficiency in power plant construction
Koivumäki, Erno (2022)
Koivumäki, Erno
2022
Rakennustekniikan DI-ohjelma - Master's Programme in Civil Engineering
Rakennetun ympäristön tiedekunta - Faculty of Built Environment
This publication is copyrighted. You may download, display and print it for Your own personal use. Commercial use is prohibited.
Hyväksymispäivämäärä
2022-02-07
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi:tuni-202201191432
https://urn.fi/URN:NBN:fi:tuni-202201191432
Tiivistelmä
The purpose of this study was to define suitable measuring items and a proper way to use them when measuring subcontractor work efficiency in a power plant construction site. As a part of the study, a database that includes the definitions and will be used to store the collected data, was created.
In addition to studying existing literature on the topic, the documents and processes of the target company were examined and employees that are working on site and subcontractor related issues were interviewed. The database was created using the expertise of multiple people from different areas.
The results of the study are a database that is ready to be implemented and instructions how to do it. These instructions include recommendations for the roles in the company that are the best fit of handling the database, information about in which part of the project to import data to the database and what are the best situations to use and analyse the data that has been collected to the database.
The study succeeded in its goal for the most part. The use of the database was not tested during the study, so it only works as the basis for work efficiency measuring that needs to be continued and improved further in the future.
In addition to studying existing literature on the topic, the documents and processes of the target company were examined and employees that are working on site and subcontractor related issues were interviewed. The database was created using the expertise of multiple people from different areas.
The results of the study are a database that is ready to be implemented and instructions how to do it. These instructions include recommendations for the roles in the company that are the best fit of handling the database, information about in which part of the project to import data to the database and what are the best situations to use and analyse the data that has been collected to the database.
The study succeeded in its goal for the most part. The use of the database was not tested during the study, so it only works as the basis for work efficiency measuring that needs to be continued and improved further in the future.