Deterministic and Probabilistic Risk Management Approaches in Construction Projects: A Systematic Literature Review and Comparative Analysis

Khodabakhshian, Ania; Puolitaival, Taija; Kestle, Linda (2023-05)

 
Avaa tiedosto
buildings-13-01312-v2.pdf (4.297Mt)
Lataukset: 



Khodabakhshian, Ania
Puolitaival, Taija
Kestle, Linda
05 / 2023

Buildings
1312
doi:10.3390/buildings13051312
Näytä kaikki kuvailutiedot
Julkaisun pysyvä osoite on
https://urn.fi/URN:NBN:fi:tuni-202505095123

Kuvaus

Peer reviewed
Tiivistelmä
Risks and uncertainties are inevitable in construction projects and can drastically change the expected outcome, negatively impacting the project’s success. However, risk management (RM) is still conducted in a manual, largely ineffective, and experience-based fashion, hindering automation and knowledge transfer in projects. The construction industry is benefitting from the recent Industry 4.0 revolution and the advancements in data science branches, such as artificial intelligence (AI), for the digitalization and optimization of processes. Data-driven methods, e.g., AI and machine learning algorithms, Bayesian inference, and fuzzy logic, are being widely explored as possible solutions to RM domain shortcomings. These methods use deterministic or probabilistic risk reasoning approaches, the first of which proposes a fixed predicted value, and the latter embraces the notion of uncertainty, causal dependencies, and inferences between variables affecting projects’ risk in the predicted value. This research used a systematic literature review method with the objective of investigating and comparatively analyzing the main deterministic and probabilistic methods applied to construction RM in respect of scope, primary applications, advantages, disadvantages, limitations, and proven accuracy. The findings established recommendations for optimum AI-based frameworks for different management levels—enterprise, project, and operational—for large or small data sets.
Kokoelmat
  • TUNICRIS-julkaisut [23470]
Kalevantie 5
PL 617
33014 Tampereen yliopisto
oa[@]tuni.fi | Tietosuoja | Saavutettavuusseloste
 

 

Selaa kokoelmaa

TekijätNimekkeetTiedekunta (2019 -)Tiedekunta (- 2018)Tutkinto-ohjelmat ja opintosuunnatAvainsanatJulkaisuajatKokoelmat

Omat tiedot

Kirjaudu sisäänRekisteröidy
Kalevantie 5
PL 617
33014 Tampereen yliopisto
oa[@]tuni.fi | Tietosuoja | Saavutettavuusseloste